Traffic signal programme 2021 to 2022

Location Description of works Status
Embankment Road/Elliot Road Traffic Signal refurbishment  Completed June 2021
Ferry Road/Park Avenue Traffic Signal refurbishment  Expected completion September 2021
Ham Drive/Honicknowle Lane Traffic Signal refurbishment  Completed July 2021
Millbay Road/The Crescent  Traffic Signal refurbishment  Completed April 2021
North Cross Roundabout/Saltash Road Traffic Signal refurbishment  Completed July 2021
Notte Street/Hoe Approach Traffic Signal refurbishment  Completed May 2021
Sutton Road/Thistle Park Traffic Signal refurbishment  Expected completion September 2021
Wolseley Road/Auckland Road Traffic Signal refurbishment  Expected completion October 2021