Plymouth City Council (PCC), South Hams District Council (SHDC) and West Devon Borough Council (WDBC) submitted the Plymouth and South West Devon Joint Local Plan (JLP) to the Secretary of State on 31 July 2017. View the Adopted Plymouth and South West Devon Joint Local Plan.
Plymouth City Council (PCC), South Hams District Council (SHDC) and West Devon Borough Council (WDBC) submitted the Plymouth and South West Devon Joint Local Plan (JLP) to the Secretary of State on 31 July 2017.
The Inspector appointed to examine the Plan was Wendy Burden BA DipTP MRTPI with Inspector Yvonne Wright BSc (Hons) DIPT&CP MSc MRTPI appointed to assist.
The Programme Officer responsible for assisting the Inspectors with the examination was Robert Young.
The Examination Library below provides access to all of the documentation associated to the examination of the Local Plan.
EXL1 | Examination Library (Version 57) | PCC, SHDC and WDBC | March 2019 |
- 19 March 2019
- Inspectors' Final Report received and published
- 5 March 2019
- Schedule of and summary response to representations on Additional and Policy Map Modifications (MM10) added
- Examination Library updated (EXL1)
- 15 January 2019
- Schedule of and summary response to representations on Main Modifications (MM9) added
- Examination Library updated (EXL1)
- 22 October 2018
- Consultation commenced on the Main Modifications and Additional/Map modifications to the Submission version of the JLP, please visit the Modifications consultation page for more information. This consultation is due to end on 3 December 2018 at 5pm
- Examination Library updated (EXL1)
- List of documents added
- 12 September 2018
- Examination Library updated (EXL1)
- Inspectors' response to the Councils' letter of 23 August 2018 (EXC17) added
- 23 August 2018
- Examination Library updated (EXL1)
- JLP Councils response to Inspectors' post hearing advice note (EXC16) added
- 15 August 2018
- Examination Library updated (EXL1)
- PSWD JLP Inspectors' post hearing advice note (EXC15) added
- JLP Councils note with further details in response to Inspectors’ Note EXC14 (EXD49G)added
- Note to Inspectors re. Local Green Space designations in the PPA (EXD65) added
- Note to Inspectors on DEV26 (EXD66) added
- Additional data re. Totnes, Ivybridge and Dean Prior AQMA April 2018 (EXD67) added
- Map showing application information for Salcombe TTV29.20 (EXD68) added
- Note to Inspectors re. Strategic Green Space (EXD69) added
- Note to Inspectors re. DEV10 point 6 (EXD70) added
- Note to Inspectors re. NSSS justification for TTV (EXD71) added
- 20 June 2018
- Examination Library updated (EXL1)
- Plymouth Policy Area Housing Supply Note (EXD64) added
- 4 June 2018
- Examination Library updated (EXL1)
- Thriving Towns and Villages Housing Supply Note (EXD63) added
- 18 May 2018
- Examination Library updated (EXL1)
- Inspectors' letter to the Councils regarding the Habitats Regulations Assessment (EXD62) added
- JLP Councils response to the Inspectors' letter regarding the Habitats Regulations Assessment (EXD62A) added
- Natural England response to the Inspectors' letter regarding the Habitats Regulations Assessment (EXD62B) added
- 23 April 2018:
- Examination Library updated (EXL1)
- JLP Councils response to the Inspectors' request for updated housing land supply figures during the hearings (EXD61) added
- Joint Local Plan Area Housing Trajectory updated to show changes to JLP allocations' site capacity and forecast delivery agreed by the Councils during the hearings (EXD61A) added
- Plymouth Policy Area Housing Trajectory updated to show changes to JLP allocations' site capacity and forecast delivery agreed by the Councils during the hearings (EXD61B) added
- Thriving Towns and Villages Policy Area Housing Trajectory updated to show changes to JLP allocations' site capacity and forecast delivery agreed by the Councils during the hearings (EXD61C) added
- 6 April 2018:
- Examination Library updated (EXL1)
- Schedule of hearing modifications (public examination) - List 7 (EXD5vii) added
- Schedule of hearing modifications (public examination) - List 8 (EXD5viii) added
- 4 April 2018:
- Examination Library updated (EXL1)
- Map showing secondary schools (with a 400m buffer), primary shopping areas and centre boundaries and A5 uses in Plymouth (EXD16A) added
- 26 March 2018:
- Examination Library updated (EXL1)
- Matter 8B Hearing Statement Appendix: Councillor John Green (PS8B-6A) added
- Matter 8B Hearing Statement Appendix: Devon County Council (PS8B-7A) added
- Matter 8E Hearing Statement: Councillor Jacqi Hodgson (PS8E-3) added
- Matter 9 Hearing Statement: Nuala McDonnell (PS9-9) added
- Modbury Parish Council/Neighbourhood Plan Group: objection to site TTV29.16 Pennpark, Modbury (EXD41A) added
- 23 March 2018:
- Examination Library updated (EXL1)
- Plymouth Policy Area - Local Green Space Assessment Information (EXD58) added
- Disabled Facilities Grant information (EXD59) added
- JLP Councils note re. the aggregated number of dwellings in figure 5.8 of JLP (EXD60) added
- Extra Care Housing: Refresh of the Commissioning Strategy for Extra Care Housing (2009) (HO21) added
- Needs of the over 55s in rural Devon (HO22) added
- 20 March 2018:
- Examination Library updated (EXL1)
- Housing land supply figures for PPA and TTV (EXD57) added
- 19 March 2018:
- Examination Library updated (EXL1)
- Start to Finish: How quickly do large-scale housing sites deliver? (EXD53A) added
- Update of schedule of hearing modifications (public examination) - List 6 (EXD5vi) added due to a missing modification
- 16 March 2018:
- Examination Library updated (EXL1)
- Dartington and Totnes boundaries and sites (EXD48) added
- JLP Councils response to Inspectors' note EXC14 re. air quality (EXD49) added
- Ivybridge Air Quality Management Area (AQMA) and sites where more than 30 per cent of traffic generated by the development is likely to pass through the AQMA (EXD49A) added
- Totnes Air Quality Management Area (AQMA) and sites where more than 30 per cent of traffic generated by the development is likely to pass through the AQMA (EXD49B) added
- Air Quality Strategy (EXD49C) added
- Air Quality Action Plan for South Hams District Council (EXD49D) added
- Air Quality Annual Status Report (ASR) (EXD49E) added
- Totnes traffic flows from 2005 (EXD49F) added
- JLP Councils note to Inspectors' re. Eastern Kings Local Green Space (LGS) (EXD50) added
- JLP Councils response to EXD21 (EXD51) added
- Note to Inspectors' setting out JLP Councils position regarding objections made by Emery Planning on behalf of Wainhomes (EXD52)
- JLP Councils details and examples of past interventions which have affected the time and scale of housing delivery and how it could work in future if there is a reduction in the amount of housing being built per annum (EXD53)
- JLP Councils note re. Slapton Line (EXD54) added
- Geographical basis of the 5 year housing land supply (EXD55) added
- References provided in relation to SHLAA sites in response to Council's case on the 'constrained supply' in the TTVPA (EXD56) added
- Matter 8E Hearing Statement: Stokenham Parish Council (PS8E-2) added
- Revised Governance Topic Paper (TP6(rev)) added
- Schedule of hearing modifications (public examination) - List 6 (EXD5vi)
- 15 March 2018:
- Examination Library updated (EXL1)
- Note to Inspectors re. additional information presented at Matter 8 Hearing Session (EXD45) added
- Note to the Inspectors re. TTV29.21 (EXD46) added
- Note to Inspectors re. outstanding matters regarding PLY32 Stonehouse Barracks (EXD47) added
- 13 March 2018:
- Examination Library updated (EXL1)
- Note to the Inspectors on the matter of strategic policies (EXD44) added
- 9 March 2008:
- Examination Library updated (EXL1)
- Slapton Coastal Zone Management Main Study: Executive Summary (T34)
- Slapton Coastal Zone Management Main Study Volume 1: Phase 1 Report (I) (T34A)
- Slapton Coastal Zone Management Main Study Volume 2: Phase 1 Report (II) (T34B)
- Slapton Coastal Zone Management Main Study Volume 3: Phase 2 Report (T34C)
- Slapton Coastal Zone Management Main Study: Business Survey Report (T34D)
- Slapton Coastal Zone Management Main Study Volume 3: Annex A - Consultation Addendum (T34E)
- 8 March 2018:
- Examination Library updated (EXL1)
- Inspectors' note: Air quality in South Hams (EXC14) added
- Amended Matter 8D Hearing Statement: Rattery Parish Council (PS8D-1A) added
- Corrections to Appendices D, E and G in the amended Matter 8D Hearing Statement (PSD-1Ai) added
- 7 March 2018:
- Examination Library updated (EXL1)
- Update on the hearing dates and venues added
- Joint Local Plan Examination: Inspectors' Draft Hearing Programme V5 (EXC8D) added
- 5 March 2018:
- Examination Library updated (EXL1)
- Better Understanding Coastal Flood Risk in Plymouth: Role of Plymouth Breakwater (EN40) added
- Changes requested by Dartington Parish Council and Neighbourhood Plan: 27 February Hearing Matter 8 (EXD40) added
- Plymouth and South West Devon Joint Local Plan housing increases as percentage of 2011 Census parish/town figures (EXD41) added
- Further details of the temporary school building on the Broom Park allocation (EXD42) added
- Representation and note for support of a Further Minor Modification in EXC10Ai re. amending the Strategy for TTV Policy Area, Figure 5.8 (EXD43) added
- 2 March 2018:
- Examination Library updated (EXL1)
- The JLP Councils amendment to Matter 8 Hearing Statement CS8 paragraph 8.17 (EXD35) added
- Schedule of hearing modifications (public examination) - List 5 (EXD5v) added
- Additional representations in respect of the West Devon SHLAA (EXD37) added
- Further written comments relating to the West Devon SHLAA identifying a limited amount of suitable, achievable and deliverable housing sites (EXD38) added
- Additional information in respect of the assessment of the site at Callington Road assessed in the West Devon SHLAA (EXD39)
- Land of Callington Road concept plan (EXD39A) added
- Local Plan Representation: Preliminary Transport Appraisal, Land North of Callington Road (EXD39B) added
- Landscape and Visual Appraisal Summary, Land North of Callington Road (EXD39C) added
- Land North of Callington Road, Tavistock Development Framework (EXD39D) added
- 1 March 2018:
- Please note that due to the severe weather the examination hearings in Tavistock on 1 March 2018 have been cancelled. We will be letting everyone know when the sessions are rescheduled in due course.
- Examination Library updated (EXL1)
- Response to the Inspectors' request re. West Devon SHLAA in relation to the distribution of housing sites to the Thriving Towns and Villages Policy Area and particularly to West Devon (EXD36) added
- 26 February 2018:
- Examination Library updated (EXL1)
- Salcombe NDP Group response to EXD9 question (EXD29) added
- Matter 12 Hearing Statement: WYG re. EXD9 (EXD30) added
- Matter 12 Hearing Statement: Persimmon Homes re. EXD9 (EXD31) added
- Report on the Examination of the South Worcestershire Development Plan (EXD32) added
- Stage 1 of the Examination of the South Worcestershire Development Plan: Inspector's interim conclusions on the stage 1 matters (EXD33) added
- Stage 1 of the Examination of the South Worcestershire Development Plan: Inspector's further interim conclusions on the outstanding Stage 1 matters (EXD34) added
- Joint Local Plan Examination: Inspectors' Draft Hearing Programme V4 (EXC8C) added
- 24 February 2018:
- Examination Library updated (EXL1)
- Statement of Common Ground between the JLP Councils, Dartington Hall Trust and Historic England (SCG11) added
- 23 February 2018:
- Examination Library updated (EXL1)
- Updated Integrated Assessment to incorporate changes agreed in Statement of Common Ground with Natural England (tracked changes) (EXD25) added
- Appendix III(a): SA/SEA Criteria and Issues to Consider of the Integrated Assessment (EXD25A) added
- Updated Appendix VII (Site Selection Methodology) of the Integrated Assessment to incorporate changes agreed in Statement of Common Ground with Natural England (tracked changes) (EXD25B) added
- Schedule of hearing modifications (public examination) - List 4 (EXD5iv) added
- Matter 8D Hearing Statement: Rattery Parish Council (PS8D-1) added
- Note re. Figure 3.2 with notes for Ringmore Village (EXD26) and Note re. Walking times to shops for Ringmore Village (EXD26A)
- Modbury Parish Council response to EXD9 question - Pennparks site (EXD27) added
- Note re. Ringmore Score Sheet (EXD28) added
- Matter 8C Hearing Statement: Modbury Society (PS8C-3) added
- 21 February 2018:
- Letter from Sutton Harbour Holdings re. Fish Quay (EXD23) added
- Ivybridge Neighbourhood Plan - Adopted Version (EXD24) added
- 19 February 2018:
- Appendix 4 of Matter 7C Hearing Statement for Rockspring Barwood Plymouth Limited (PS7C-3A) added
- 16 February 2018:
- Schedule of hearing modifications (public examination) - List 3 (EXD5iii) added
- Updated Habitat Regulations Assessment to incorporate changes agreed in Statement of Common Ground with Natural England (EXD22) added
- Updated Habitat Regulations Assessment (SUB10) to incorporate changes agreed in Statement of Common Ground with Natural England (tracked changes) (EXD22A) added
- 15 February 2018:
- Examination Library updated (EXL1)
- Letter from Montagu Evans to inspectors re. response to T33 (EXD19) added
- Letter from Montagu Evans to inspectors re. SA criteria (EXD20) added
- Letter from Highways England to inspectors re. DEV31 (EXD21) added
- 9 February 2018:
- Examination Library updated (EXL1)
- Report on the examination into the Derriford and Seaton Area Action Plan 2006 to 2021 (EXD14) added
- JLP Councils' note re. Draft Derriford Commercial Centre Masterplan Summary Report and Derriford Commercial Centre - South Masterplan Summary Report (EXD15) added
- Map showing secondary schools (with a 400m buffer) and primary shopping areas and centre boundaries in Plymouth (EXD16) added
- Schedule of hearing modifications (public examination) - List 2 (EXD5ii) added
- Plymstock geology map showing mineral safeguarding area and 500m buffer from limestone deposit (EXD17) added
- Brownfield sites rejected at Reg18 stage in Plymouth Policy Area (EXD18) added
- 8 February 2018:
- Examination Library updated (EXL1)
- Plan showing existing general aviation services in Joint Local Plan Area (EXD12A) added
- Sutton Harbour Holding Reg.19 Representations Appendix 2, contextual plan of the former airport site (EXD12B) added
- Ombudsman Report on an investigation into Plymouth City Council regarding noise at Plymouth Airport (EXD12C) added
- Ombudsman Report on an investigation into Plymouth City Council regarding noise at Plymouth Airport (EXD12D) added
- Ombudsman Report on an investigation into Plymouth City Council regarding noise at Plymouth Airport (EXD12E) added
- Kinterbury Point, HMAD Bullpoint proposed helipad planning permission (15/01271/FUL) (EXD12F) added
- Woolwell proposed allocation and relevant boundary plan (EXD12G) added
- Letter from Plymouth City Council re. secondary school places (EXD13) added
- 7 February 2018:
- Examination Library updated (EXL1)
- Updated version of Statement of Common Ground between the JLP Councils and Rockspring Barwood Plymouth Ltd (SCG1i) added
- Excerpt of Adopted Torbay Local Plan, 2012 to 2030 (EXD11) added
- 6 February 2018:
- Examination Library updated (EXL1)
- Inspectors' note on the assessment of housing need and land supply (EXD9) added
- Plymouth Report (O16) added
- Letter from Homes England re. Land at Coypool Park (EXD10) added
- 5 February 2018:
- Examination Library updated (EXL1)
- Officer report for planning application 08/01968/OUT (EXD7A) added
- Statement of Common Ground between the JLP Councils and Sutton Harbour Holdings (SCG10) added
- Updated version of Statement of Common Ground between the JLP Councils and South West Strategic Developments (SCG7i) added
- 2 February 2018:
- Examination Library updated (EXL1)
- JLP Councils' note re. local migration figures from DCC (EXD2) added
- JLP Councils' note re. historic delivery compared with relevant plan requirement (EXD3) added
- JLP Councils' note re. historic number of dwellings with pp and not started in South Hams and West Devon (EXD4) added
- Schedule of hearing modifications (public examination) - List 1 (EXD5i) added
- Text of amendments proposed by Tamerton Foliot Village Conservation Society (EXD6) added
- Decision notice for planning application 08/01968/OUT (EXD7) added
- Decision notice for planning application 09/00822/FUL (EXD8) added
- Data showing the general and scheduled air traffic movements at Plymouth Airport 2002 to 2011 (T33) added
- 31 January 2018:
- Examination Library updated (EXL1)
- Matter 4B Hearing Statement: FlyPlymouth Ltd - Further statement (PS4B-2A), Matter 4B Hearing Statement Appendix: FlyPlymouth Ltd (PS4B-2B) and Matter 4B Hearing Statement Appendix: FlyPlymouth Ltd (PS4B-2C) added
- Matter 3 Hearing Statement Appendix: Barratt David Wilson Homes South West (PS3-1B)
- 30 January 2018:
- Examination Library updated (EXL1)
- JLP Councils' Hearing Opening Statement (EXD1) added
- Further Written Representations on PLY55 (FRW-3) and Further Written Representations on PLY55, Appendix 11 (FRW-3A) added
- JLP Councils' response to Matter 3 (Housing) (CS3L) additional Appendix added
- 29 January 2018:
- Examination Library updated (EXL1)
- Safe Operating Practices at Unlicensed Aerodromes (T30), Aviation Policy Framework (T31) and General Aviation Strategy (T32) added
- JLP Councils' corrections in response to Inspectors' queries regarding TP3(rev) and CS3 (EXC13) added
- 25 January 2018:
- Examination Library updated (EXL1)
- PS8B-4 removed from the website
- Position Statement Five: Plymouth and South West Devon Joint Local Plan Transport Strategy Working Group (T29) and Plymouth and South West Devon Joint Local Plan – 2034 Forecast SATURN model results (T20ii) added
Please note: These additional evidence base documents are an evolution of the documents already within the Examination Library.
- 23 January 2018:
- Examination Library updated (EXL1)
- Matter 3.1 Hearing Statement Additional Letter (PS3-7L) and Appendix (PS3-7M) added
- Joint Local Plan Examination: Inspectors' Draft Hearing Programme V3 (EXC8B) added
- Inspectors' note assessing the supply of housing land (EXC12) added
- 17 January 2018:
- Examination Library updated (EXL1)
- Joint Local Plan Examination: Inspectors' Draft Hearing Programme V2 (EXC8A) added
- 12 January 2018:
- Examination Library updated (EXL1)
- 11 January 2018:
- Participants Hearing Statements (PS), Further Written Representations on Matter 7C and PLY44 (FRW-1) and Further Written Representations on Vision Statement, PLY27 and DEV1 (FRW-2) added
- 8 January 2018:
- Examination Library updated (EXL1)
- Revised Housing Topic Paper added (TP3(rev))
Please note: This document updates TP3 which became out of date when the updated housing trajectories to the March 2017 point (TP3E, TP3F, TP3G) were produced in response to EXC2. - Joint Local Plan - Plymouth, South Hams, West Devon: Market Signals Update (HO19) and Joint Local Plan - Plymouth, South Hams, West Devon: Testing and establishing the Plymouth Housing Market Area (HO20) documents added
Please note: These documents were published alongside the JLP consultation in July 2016, and were superseded by the SHMA Part 1 (HO13), they're being re-published because they informed the early stage of JLP preparation and are referred to in the revised Housing Topic Paper (TP3(rev)) which is the audit trail about the use of evidence which informed the preparation of the JLP. - Housing Needs of Physically Disabled People in Plymouth (HO18) document
Please note: This document was produced by PCC's Housing Delivery Team to assess disabled housing need in Plymouth and quantify estimates for the delivery of specialist forms of housing (assist delivery of specialist forms of housing). The Councils believe it assists to clarify the approach taken in the JLP in respect of questions raised by the Inspectors in Matter 10, and therefore has been added to the Examination Library. - Schedule of Potential Further Modifications (EXC10Ai) added to the examination correspondence
- Examination Hearing Statements (CS1 to CS11) added
- Examination Statements of Common Ground (SCG1 to SCG9) added
- Governance Topic Paper (TP6) added
- Plymouth and South West Devon Joint Local Plan 2034 Forecast SATURN model results summary (T20i), 2034 Forecast SATURN model results summary (Spatial Scenarios) (T20A), Position Statement Four: Plymouth and South West Devon Joint Local Plan Transport Strategy Working Group (T27) and Memorandum of Understanding: Plymouth and South West Devon Joint Local Plan Transport Strategy Working Group added (T28)
Please note: The previously published transport evidence base includes a number of position statements between the three Highway Authorities (which form the JLP Transport Strategy Working Group) within the JLP area (and accompanying model output reports) which reference that further statements and modelling reports would be produced. As set out in the evidence base the transport work informing the delivery of the JLP is an iterative process and the work of the Transport Strategy Working Group has continued post publishing the evidence base at the time of the Regulation 19 consultation and since the submission of the JLP. The additional evidence base documents which have been added to the library are an evolution of the documents already within the Examination Library.
- 15 December 2017:
- Sutton Harbour Holdings letter to inspectors (EXC11) and Inspectors' reply to Sutton Harbour Holdings (EXC11A) added to the examination correspondence
- Examination Library updated (EXL1)
- 13 December 2017:
- Examination Library updated (EXL1)
- Joint Local Plan Authorities cover letter regarding potential modifications (EXC10), Plymouth and South West Devon Joint Plan: Schedule of potential modifications (EXC10A) and Plymouth and South West Devon Joint Local Plan: Potential modifications (EXC10B) added to the examination correspondence
- 5 December 2017:
- Examination Library updated (EXL1)
- EXC9 (amalgamated TP3E, TP3F, TP3G) added to the examination correspondence
- 30 November 2017:
- Examination Library updated (EXL1)
- Joint Local Plan Area Housing Trajectory updated to the March 2017 monitoring point (TP3E), Plymouth Policy Area Housing Trajectory updated to the March 2017 monitoring point (TP3F), Thriving Towns and Villages Policy Area Housing Trajectory updated to the March 2017 monitoring point (TP3G), Plymouth Policy Area Housing Trajectory Agreement (TP3H) and Thriving Towns and Villages Housing Trajectory Agreement (TP3I) added to the evidence base under 'Topic Papers'
- 10 November 2017:
- Inspectors' Guidance Note (EXC6) added to the examination correspondence
- Inspectors' Matters Issues and Questions (EXC7) added to the examination correspondence
- Inspectors' Draft Hearing Programme V1 (EXC8) added to the examination correspondence
- Examination Library updated (EXL1)
- 1 November 2017:
- Councils' response to Inspectors' question set out in EXC4 (EXC4A) added to the examination correspondence
- Examination Library updated (EXL1)
- 16 October 2017:
- Inspectors' note re alternative or omission sites (EXC5) added to the examination correspondence
- Examination Library updated (EXL1)
- 11 October 2017:
- Proposed Joint Local Plan Governance Framework (EXC3F) added to the examination correspondence
- Examination Library updated (EXL1)
- 9 October 2017:
- Received Inspectors' note to councils regarding the Secretary of State consultation proposals: Planning for the right homes in the right places (EXC4) and added to the examination correspondence
- 6 October 2017:
- Examination Library updated (EXL1)
- JLP Authorities Response to EXC2 published, including appendices (EXC3) and added to the examination correspondence
- Evolution of the Joint Local Plan timeline (EXC3A) added to the examination correspondence
- New contents page for the Joint Local Plan (EXC3B also SUB1B) added to the examination correspondence
- Reformatted Housing Trajectories (amalgamated pdf of three trajectories) (EXC3C also TP3Ai, TP3Bi, TP3Ci) added to the examination correspondence and the evidence base under 'Topic Papers'
- Summary of allocated and rejected sites (EXC3D) added to the examination correspondence
- Correspondence from the statutory consultees on the Scoping Report for the draft SA (EXC3E) added to the examination correspondence
- New contents for SUB1 published (SUB1B also EXC3B) and added to the submission documents and the examination correspondence
- Reformatted housing trajectories published (TP3Ai, TP3Bi, TP3Ci also EXC3C) and added to the evidence base under 'Topic Papers'
- Town benchmarking reports added regarding Tavistock and Okehampton (EC12, EC13, EC14, EC15, EC16) added to the evidence base under 'Economy'
- Minerals evidence base (O12, O13, O14, O15) added to the evidence base under 'Other'
- Joint Local Plan - Plymouth, South Hams, West Devon: Establishing the Objectively Assessed Need (HO17) added to the evidence base under 'Housing'
- Replaced previous version of Shoreline Management Plan Review (SMP2) Durlston Head to Rame Head (EN8) which was only part of the document
- 4 September 2017:
- Examination Library updated (EXL1)
- Habitat Regulations Assessment (Draft) (JLP22) added to the evidence base under 'Past consultation documents'
- Received preliminary letter from the Planning Inspectors to the Councils, containing questions and information about how the Inspectors intend to proceed with the examination process (EXC2) and added to the examination correspondence
- SUB1A added to the submission documents
- 31 August 2017:
- Submission Document (with tracked changes) showing the minor changes that were made from the Regulation 19 Consultation Document to the Submission Document (SUB1A) added to the submission documents
- 31 July 2017:
- Received letter from Planning Inspectorate (PINS) appointing an Inspector to examine the Plymouth and South West Devon Joint Local Plan (EXC1) and added to the examination correspondence
- Plymouth and South West Devon Joint Local Plan submitted to the Secretary of State for Examination
On 15 August 2018 Plymouth City Council (PCC), South Hams District Council (SHDC) and West Devon Borough Council (WDBC) received a Post Hearing Advice Note (EXC15) from the Planning Inspectors. Consultation on both the Main Modifications to the Submission version of the JLP and the Additional/Policies Map Modifications ran from 22 October 2018 to 3 December 2018.
Please see below documents associated with this consultation:
Main Modifications
To take account of the Main Modifications, some background documents were also produced or updated:
TP3(rev2) |
Revised Housing Topic Paper (Provision and Supply) Addendum |
PCC, SHDC and WDBC | October 2018 |
TP3(rev2)A |
Revised Housing Topic Paper (Provision and Supply) Addendum (tracked changes) |
PCC, SHDC and WDBC | October 2018 |
TP3J | Joint Local Plan Area Housing Trajectory March 2017 Monitoring Point, incorporating proposed Main Modifications | PCC, SHDC and WDBC | October 2018 |
TP3K | Plymouth Policy Area Housing Trajectory March 2017 Monitoring Point, incorporating proposed Main Modifications | PCC, SHDC and WDBC | October 2018 |
TP3L | Thriving Towns and Villages Policy Area Housing Trajectory March 2017 Monitoring Point, incorporating proposed Main Modifications | PCC, SHDC and WDBC | October 2018 |
TP4(rev) |
Revised Employment Topic Paper |
PCC, SHDC and WDBC | October 2018 |
TP4(rev)A |
Revised Employment Topic Paper (tracked changes) |
PCC, SHDC and WDBC | October 2018 |
TP7 | Development in Plymouth's Urban Fringe Topic Paper | PCC, SHDC and WDBC | October 2018 |
EN31(rev) |
Revised Plymouth Greenspace Policy Development Process |
PCC, SHDC and WDBC | August 2018 |
Councils Hearing Statements
Participants Hearing Statements
Matter 1 | |||
PS1-1 | Matter 1 (and others) Hearing Statement: Natural England | Natural England | January 2018 |
Matter 2 | |||
PS2-1 | Matter 2 Hearing Statement: Wainhomes (South West) Holding Ltd | Emery Planning on behalf of Wainhomes (South West) Holding Ltd | January 2018 |
PS2-2 | Matter 2 Hearing Statement: Heynes Planning | Heynes Planning on behalf of D Stratton/R and B Bennet/J Stratton, Place Land LLP and Diocese of Plymouth | January 2018 |
PS2-3 | Matter 2 Hearing Statement: Persimmon Homes | Persimmon Homes | January 2018 |
PS2-4 | Matter 2 Hearing Statement: Councillor Jacqi Hodgson | Councillor Jacqi Hodgson | January 2018 |
Matter 3 | |||
PS3-1 | Matter 3 Hearing Statement: Barratt David Wilson Homes South West | LRM Planning Limited on behalf of Barratt David Wilson Homes South West | January 2018 |
PS3-1A | Matter 3 Hearing Statement Appendix: Barratt David Wilson Homes South West | Wessex Economics on behalf of Barratt David Wilson Homes South West | January 2018 |
PS3-1B | Matter 3 Hearing Statement Appendix: Barratt David Wilson Homes South West - note that addresses some errors contained in PS3-1 | Wessex Economics on behalf of Barratt David Wilson Homes South West | January 2018 |
PS3-2 | Matter 3 Hearing Statement: Wainhomes (South West) Holding Ltd | Emery Planning on behalf of Wainhomes (South West) Holding Ltd | January 2018 |
PS3-3 | Matter 3 Hearing Statement: Land Value Alliances Ltd | Walsingham Planning on behalf of Land Value Alliances Ltd | January 2018 |
PS3-4 | Matter 3 Hearing Statement: Bloor Homes South West Ltd and Millwood Homes SW Ltd | WYG on behalf of Bloor Homes South West Ltd and Millwood Homes SW Ltd | January 2018 |
PS3-5 | Matter 3 Hearing Statement: Mark Scoot, Taylor Wimpey (Exeter) and Bovis Homes Ltd | Lichfields on behalf of Mark Scoot, Taylor Wimpey (Exeter) and Bovis Homes Ltd | January 2018 |
PS3-5A | Matter 3 Hearing Statement Appendices: Mark Scoot, Taylor Wimpey (Exeter) and Bovis Homes Ltd | Lichfields on behalf of Mark Scoot, Taylor Wimpey (Exeter) and Bovis Homes Ltd | January 2018 |
PS3-6 | Matter 3 Hearing Statement: Persimmon Homes | Persimmon Homes | January 2018 |
PS3-7 | Matter 3.1 Hearing Statement: PCL Planning | PCL Planning | January 2018 |
PS3-7A | Matter 3.1 Hearing Statement Appendix 1: PCL Planning | DTZ Pieda Consulting | January 2018 |
PS3-7B | Matter 3.1 Hearing Statement Appendix 2: PCL Planning | The Planning Inspectorate | January 2018 |
PS3-7C | Matter 3.1 Hearing Statement Appendix 3: PCL Planning | PCC, Devon County Council, Torbay Council and Dartmoor National Park Authority | January 2018 |
PS3-7D | Matter 3.1 Hearing Statement Appendix 4: PCL Planning | Dartmoor National Park Authority | January 2018 |
PS3-7E | Matter 3.1 Hearing Statement Appendix 5: PCL Planning | The Planning Inspectorate | January 2018 |
PS3-7F | Matter 3.1 Hearing Statement Appendix 6: PCL Planning | Government Office for the South West | January 2018 |
PS3-7G | Matter 3.1 Hearing Statement Appendix 7: PCL Planning | PCL Planning | January 2018 |
PS3-7H | Matter 3.1 Hearing Statement Appendix 8: PCL Planning | PCC | January 2018 |
PS3-7I | Matter 3.1 Hearing Statement Appendix 9: PCL Planning | PCC, SHDC and WDBC | January 2018 |
PS3-7J | Matter 3.1 Hearing Statement Appendix 10: PCL Planning | The Planning Inspectorate | January 2018 |
PS3-7K | Matter 3.1 Hearing Statement Appendices List: PCL Planning | PCL Planning | January 2018 |
PS3-7L | Matter 3.1 Hearing Statement Additional Letter: PCL Planning | PCL Planning | January 2018 |
PS3-7M | Matter 3.1 Hearing Statement Additional Letter Appendix | GVA on behalf of PCC, SHDC, WDBC, Cornwall Council and Dartmoor National Park Authority | July 2013 |
PS3-8 | Matter 3.2 Hearing Statement: PCL Planning | PCL Planning | January 2018 |
PS3-9 | Matter 3.3 Hearing Statement: PCL Planning | PCL Planning | January 2018 |
Matter 4 | |||
PS4A-1 | Matter 4A Hearing Statement: Highways England | Highways England | January 2018 |
PS4A-2 | Matter 4A Hearing Statement: Highways England | CH2M on behalf of Highways England | January 2018 |
PS4A-2A | Matter 4A Hearing Statement Appendix A: Highways England | Halcrow Group Ltd | January 2018 |
PS4A-2B | Matter 4A Hearing Statement Appendix B: Highways England | Highways England | January 2018 |
PS4A-2C | Matter 4A Hearing Statement Appendix C: Highways England | CH2M on behalf of Highways England | January 2018 |
PS4A-2D | Matter 4A Hearing Statement Appendix D: Highways England | TRL Limited | January 2018 |
PS4A-3 | Matter 4A Hearing Statement: Devon County Council | Devon County Council | January 2018 |
PS4B-1 | Matter 4A Hearing Statement: Sutton Harbour Holdings PLC | Montagu Evans on behalf of Sutton Harbour Holdings PLC | January 2018 |
PS4B-1A | Matter 4B Hearing Statement Appendix 5: Sutton Harbour Holdings PLC | Leslie Jones Architecture | January 2018 |
PS4B-2 | Matter 4B Hearing Statement: FlyPlymouth Ltd | FlyPlymouth Ltd | January 2018 |
PS4B-2A | Matter 4B Hearing Statement Appendix: FlyPlymouth Ltd - Further statement | FlyPlymouth Ltd | January 2018 |
PS4B-2B | Matter 4B Hearing Statement Appendix: FlyPlymouth Ltd - Plymouth Airport - Response to SHH: Noise | FlyPlymouth Ltd | January 2018 |
PS4B-2C | Matter 4B Hearing Statement Appendix: FlyPlymouth Ltd - Aviation: Written question | FlyPlymouth Ltd | January 2018 |
Matter 5 | |||
PS5-1 | Matter 5 Hearing Statement: Premier Marinas (Dart) Ltd | CBRE on behalf of Premier Marinas (Dart) Ltd | January 2018 |
Matter 6 | |||
PS6-1 | Matter 6 Hearing Statement: KFC (GB) Limited | SSA Planning Limited on behalf of KFC (GB) Limited | January 2018 |
PS6-2 | Matter 6 Hearing Statement: Drake Circus Limited Partnership | Deloitte LLP on behalf of Drake Circus Limited Partnership | January 2018 |
PS6-3 | Matter 6 Hearing Statement: Co-operative Group Food Ltd | Pegasus Planning Group on behalf of Co-operative Group Food Ltd | January 2018 |
Matter 7 | |||
PS7A-1 | Matter 7A and 7C Hearing Statement: Devon County Council | Devon County Council | January 2018 |
PS7B-1 | Matter 7B Hearing Statement: Drake Circus Limited Partnership | Deloitte LLP on behalf of Drake Circus Limited Partnership | January 2018 |
PS7B-2 | Matter 7B Hearing Statement: Hoe Neighbourhood Forum | Hoe Neighbourhood Forum | January 2018 |
PS7B-3 | Matter 7B Hearing Statement: Sutton Harbour Holdings PLC | PCL Planning on behalf of Sutton Harbour Holdings PLC | January 2018 |
PS7B-3A | Matter 7B Appendix 1: Sutton Harbour Holdings PLC | PCC | January 2018 |
PS7B-3B | Matter 7B Appendix 2: Sutton Harbour Holdings PLC | The High Court of Justice | January 2018 |
PS7C-1 | Matter 7C Hearing Statement and Appendices: Sutton Harbour Holdings PLC | Montagu Evans on behalf of Sutton Harbour Holdings PLC | January 2018 |
PS7C-2 | Matter 7C Hearing Statement: Co-operative Group Food Ltd |
Pegasus Planning Group on behalf of Co-operative Group Food Ltd |
January 2018 |
PS7C-3 | Matter 7C Hearing Statement: Rockspring Barwood Plymouth Limited | Boyer Planning on behalf of Rockspring Barwood Plymouth Limited | January 2018 |
PS7C-3A | Matter 7C Appendix 4: Rockspring Barwood Plymouth Limited | Boyer Planning on behalf of Rockspring Barwood Plymouth Limited | February 2018 |
PS7D-1 | Matter 7D Hearing Statement: Sherford New Community Consortium | CMYK on behalf of the Sherford New Community Consortium | January 2018 |
PS7E-1 | Matter 7E Hearing Statement: D Stratton, R and B Bennett and J Stratton | Heynes Planning on behalf of D Stratton/R and B Bennet/J Stratton | January 2018 |
Matter 8 | |||
PS8A-1 | Matter 8A Hearing Statement: Wainhomes (South West) Holding Ltd | Emery Planning on behalf of Wainhomes (South West) Holding Ltd | January 2018 |
PS8A-2 | Matter 8A Hearing Statement: Place Land LLP | Place Land LLP | January 2018 |
PS8A-3 | Matter 8A Hearing Statement: Dartington Hall Trust | Lichfields on behalf of the Dartington Hall Trust | January 2018 |
PS8A-3A | Matter 8A Hearing Statement Appendices 1 and 2: Dartington Hall Trust | Lichfields on behalf of the Dartington Hall Trust | January 2018 |
PS8A-3B | Matter 8A Hearing Statement Appendix 3: Dartington Hall Trust | Studio Partington on behalf of the Dartington Hall Trust | January 2018 |
PS8A-3C | Matter 8A Hearing Statement Appendix 4: Dartington Hall Trust | Hydrock on behalf of the Dartington Hall Trust | January 2018 |
PS8A-3D | Matter 8A Hearing Statement Appendix 5: Dartington Hall Trust |
Tyler Grange LLP on behalf of the Dartington Estate |
January 2018 |
PS8A-3E | Matter 8A Hearing Statement Appendix 6: Dartington Hall Trust |
EAD Ecology on behalf of the Dartington Hall Trust |
January 2018 |
PS8A-3F | Matter 8A Hearing Statement Appendix 7: Dartington Hall Trust | Studio Partington on behalf of the Dartington Hall Trust | January 2018 |
PS8A-3G | Matter 8A Hearing Statement Appendix 8: Dartington Hall Trust | EAD Ecology on behalf of the Dartington Hall Trust | January 2018 |
PS8A-3H | Matter 8A Hearing Statement Appendix 9: Dartington Hall Trust | The Dartington Hall Trust | January 2018 |
PS8A-3I | Matter 8A Hearing Statement Appendix 9 Plan: Dartington Hall Trust | The Dartington Hall Trust | January 2018 |
PS8A-4 | Matter 8A Hearing Statement: Stuart Properties Ltd | Bell Cornwell on behalf of Stuart Properties Ltd | January 2018 |
PS8A-4A | Matter 8A Hearing Statement Appendix A: Stuart Properties Ltd | SHDC | January 2018 |
PS8A-4B | Matter 8A Hearing Statement Appendix B: Stuart Properties Ltd | Bell Cornwell on behalf of Stuart Properties Ltd | January 2018 |
PS8B-1 | Matter 8B Hearing Statement: Mr L N Pengelly | Mr L N Pengelly | January 2018 |
PS8B-2 | Matter 8B Hearing Statement: Mr L N Pengelly | Mr L N Pengelly | January 2018 |
PS8B-3 | Matter 8B Hearing Statement: Mr L N Pengelly | Mr L N Pengelly | January 2018 |
PS8B-4 | Number not allocated | n/a | n/a |
PS8B-5 | Matter 8B Hearing Statement: Premier Marinas (Dart) Ltd | CBRE on behalf of Premier Marinas (Dart) Ltd | January 2018 |
PS8B-6 | Matter 8B Hearing Statement: Councillor John Green | Councillor John Green | January 2018 |
PS8B-6A | Matter 8B Hearing Statement Appendix: Councillor John Green | Councillor John Green | March 2018 |
PS8B-7 | Matters 8B and 8F Hearing Statement: Devon County Council | Devon County Council | January 2018 |
PS8B-7A | Matter 8B Hearing Statement Appendix: Devon County Council | Devon County Council | March 2018 |
PS8B-8 | Matter 8B Hearing Statement: Ivybridge Town Council and Ivybridge Neighbourhood Plan Group | Ivybridge Town Council and Ivybridge Neighbourhood Plan Group | January 2018 |
PS8B-9 | Matter 8B TTV5 Hearing Statement: Millwood Homes SW Ltd | WYG on behalf of Millwood Homes SW Ltd | January 2018 |
PS8B-10 | Matter 8B TTV9 Hearing Statement: Bloor Homes South West Ltd | WYG on behalf of Bloor Homes South West Ltd | January 2018 |
PS8C-1 | Matter 8C Hearing Statement: Historic England | Historic England | January 2018 |
PS8C-2 | Matter 8C TTV29 Hearing Statement: Bloor Homes South West Ltd | WYG on behalf of Bloor Homes South West Ltd | January 2018 |
PS8C-3 | Matter 8C Hearing Statement: Modbury Society | Modbury Society | February 2018 |
PS8D-1 | Matter 8D Hearing Statement: Rattery Parish Council | Rattery Parish Council | February 2018 |
PS8D-1A | Amended Matter 8D Hearing Statement: Rattery Parish Council (corrected 7 March 2018) | Rattery Parish Council | 8 March 2018 |
PS8D-1Ai | Appendices D, E and G corrections shown in the amended Matter 8D Hearing Statement (PSD-1A) | Rattery Parish Council | 8 March 2018 |
PS8E-1 | Matter 8E Hearing Statement: Christina Torrington | Christina Torrington | January 2018 |
PS8E-2 | Matter 8E Hearing Statement: Stokenham Parish Council | Piers Spence for Stokenham Parish Council | 14 March 2018 |
PS8E-3 | Matter 8E Hearing Statement: Councillor Jacqi Hodgson | Councillor Jacqi Hodgson | March 2018 |
PS8F-1 | Matter 8F Hearing Statement: Mark Scoot | Mark Scoot | January 2018 |
PS8F-2 | Matter 8F Hearing Statement: Bovis Homes Ltd | Walsingham Planning on behalf of Bovis Homes Ltd | January 2018 |
PS8F-3 | Matter 8F Hearing Statement: Land Value Alliances Ltd | Walsingham Planning on behalf of Land Value Alliances Ltd | January 2018 |
Matter 9 | |||
PS9-1 | Matter 9 Hearing Statement: Plymouth Properties | LRM Planning on behalf of Plymouth Properties | January 2018 |
PS9-2 | Matter 9 Hearing Statement: Cann Estate | Savills on behalf of the Cann Estate | January 2018 |
PS9-3 | Matter 9 Hearing Statement: Bovis Homes Ltd | Walsingham Planning on behalf of Bovis Homes Ltd | January 2018 |
PS9-4 | Matter 9 Hearing Statement: Land Value Alliances Ltd | Walsingham Planning on behalf of Land Value Alliances Ltd | January 2018 |
PS9-5 | Matter 9 Hearing Statement: A and M Trust | WYG on behalf of A and M Trust | January 2018 |
PS9-6 | Matter 9 Hearing Statement: Donna Forshaw |
The Environmental Dimension Partnership Ltd on behalf of Donna Forshaw |
January 2018 |
PS9-7 | Matter 9 Hearing Statement: Rockspring Barwood Plymouth Limited | Boyer Planning on behalf of Rockspring Barwood Plymouth Limited | January 2018 |
PS9-8 | Number not allocated | n/a | n/a |
PS9-9 | Matter 9 Hearing Statement: Nuala McDonnell | Nuala McDonnell | 19 March 2018 |
Matter 10 | |||
PS10-1 | Matter 10 Hearing Statement: Premier Marinas (Dart) Limited | CBRE on behalf of Premier Marinas (Dart) Ltd | January 2018 |
PS10-2 | Matter 10 Hearing Statement: Bovis Homes Ltd | Walsingham Planning on behalf of Bovis Homes Ltd | January 2018 |
PS10-3 | Matter 10 Hearing Statement: Land Value Alliances Ltd | Walsingham Planning on behalf of Land Value Alliances Ltd | January 2018 |
PS10-4 | Matter 10 Hearing Statement: D Stratton, R and B Bennett and J Stratton | Heynes Planning on behalf of D Stratton/R and B Bennet/J Stratton | January 2018 |
Matter 11 | |||
No responses received | |||
Matter 12 | |||
Please see EXD29, EXD30 and EXD31 |
Further Written Representations
FRW-1 | Further Written Representations on Matter 7C and PLY44 | Wendy Haymes | January 2018 |
FRW-2 | Further Written Representations on Vision Statement, PLY27 and DEV1 | Martin Worrall | January 2018 |
FRW-3 | Further Written Representations on PLY55 | Duncan Matthews | January 2018 |
FRW-3A | Further Written Representations on PLY55, Appendix 11 | Duncan Matthews | January 2018 |
TP1 | Housing Distribution Topic Paper | PCC, SHDC and WDBC | November 2016 |
TP2 | Thriving Towns and Villages Settlement Boundary Topic Paper | PCC, SHDC and WDBC | March 2017 |
TP3 | Housing Topic Paper (Provision and Supply) | PCC, SHDC and WDBC | March 2017 |
TP3(rev) | Housing Topic Paper (Provision and Supply)
Please note: This document updates TP3 which became out of date when the updated housing trajectories to the March 2017 point (TP3E, TP3F, TP3G) were produced in response to EXC2. |
PCC, SHDC and WDBC | January 2018 |
TP3(rev2) |
Revised Housing Topic Paper (Provision and Supply) Addendum |
PCC, SHDC and WDBC | October 2018 |
TP3(rev2)A |
Revised Housing Topic Paper (Provision and Supply) Addendum (tracked changes) |
PCC, SHDC and WDBC | October 2018 |
TP3A | Joint Local Plan Area Housing Trajectory | PCC, SHDC and WDBC | March 2017 |
TP3Ai | Joint Local Plan Area Housing Trajectory (reformatted TP3A) | PCC, SHDC and WDBC | October 2017 |
TP3B | Plymouth Policy Area Housing Trajectory | PCC, SHDC and WDBC | March 2017 |
TP3Bi | Plymouth Policy Area Housing Trajectory (reformatted TP3B) | PCC, SHDC and WDBC | October 2017 |
TP3C | Thriving Towns and Villages Policy Area Housing Trajectory | PCC, SHDC and WDBC | March 2017 |
TP3Ci | Thriving Towns and Villages Policy Area Housing Trajectory (reformatted TP3C) | PCC, SHDC and WDBC | October 2017 |
TP3D | Housing Topic Paper (Provision and Supply): Errata List | PCC, SHDC and WDBC | July 2017 |
TP3E | Joint Local Plan Area Housing Trajectory updated to the March 2017 monitoring point (referenced in paragraph 1.9 of EXC3) | PCC, SHDC and WDBC | November 2017 |
TP3F | Plymouth Policy Area Housing Trajectory updated to the March 2017 monitoring point (referenced in paragraph 1.9 of EXC3) | PCC, SHDC and WDBC | November 2017 |
TP3G | Thriving Towns and Villages Policy Area Housing Trajectory updated to the March 2017 monitoring point (referenced in paragraph 1.9 of EXC3) | PCC, SHDC and WDBC | November 2017 |
TP3H | Plymouth Policy Area Housing Trajectory Agreement (referenced in paragraph 1.9 of EXC3) | PCC, SHDC and WDBC | November 2017 |
TP3I | Thriving Towns and Villages Housing Trajectory Agreement referenced in paragraph 1.9 of EXC3) | PCC, SHDC and WDBC | November 2017 |
TP3J | Joint Local Plan Area Housing Trajectory March 2017 Monitoring Point, incorporating proposed Main Modifications | PCC, SHDC and WDBC | October 2018 |
TP3K | Plymouth Policy Area Housing Trajectory March 2017 Monitoring Point, incorporating proposed Main Modifications | PCC, SHDC and WDBC | October 2018 |
TP3L | Thriving Towns and Villages Policy Area Housing Trajectory March 2017 Monitoring Point, incorporating proposed Main Modifications | PCC, SHDC and WDBC | October 2018 |
TP4 | Employment Topic Paper | PCC, SHDC and WDBC | July 2017 |
TP4(rev) |
Revised Employment Topic Paper Please note: This document updates TP4 which became out of date during the examination hearings which took place from January to March 2018 |
PCC, SHDC and WDBC | October 2018 |
TP4(rev)A |
Revised Employment Topic Paper (tracked changes) Please note: This document shows the tracked changes from the original TP4 |
PCC, SHDC and WDBC | October 2018 |
TP5 | Strategy Topic Paper | PCC, SHDC and WDBC | July 2017 |
TP6 | Governance Topic Paper | PCC, SHDC and WDBC | January 2018 |
TP6(rev) | PCC, SHDC and WDBC | March 2018 | |
TP7 | Development in Plymouth's Urban Fringe Topic Paper | PCC, SHDC and WDBC | October 2018 |
The Plymouth and South West Devon Joint Local Plan has to be soundly based on a robust, credible Evidence Base. It will be this question of 'soundness' which will be central to its examination. The Evidence Base falls under the following categories:
Other (includes infrastructure) (O)
Economy
Environment
Flooding
Heritage
HE1 | Plymouth Rapid Urban Character Study | Alan Baxter and Associates | February 2005 |
HE2 | South Hams District Design Review Assessment | The Prince's Foundation for the Built Environment | June 2009 |
HE3 | Plymouth Palmerston Forts Stage C: Strategic Summary and Individual Site Statements | URS/Scott Wilson | May 2011 |
HE4 | Heritage Impact Assessment | Plymouth City Council, South Hams District Council, West Devon Borough Council | February 2017 |
Housing
Transport
2011 |
Slapton Coastal Zone Management Main Study: Executive Summary
Prepared by Scott Wilson for Slapton Line Partnership August 2006 T34A Slapton Coastal Zone Management Main Study Volume 1: Phase 1 Report (I) Prepared by Scott Wilson for Slapton Line Partnership August 2006 T34B Slapton Coastal Zone Management Main Study Volume 2: Phase 1 Report (II) Prepared by Scott Wilson for Slapton Line Partnership August 2006 T34C Slapton Coastal Zone Management Main Study Volume 3: Phase 2 Report Prepared by Scott Wilson for Slapton Line Partnership August 2006 T34D Slapton Coastal Zone Management Main Study: Business Survey Report Roger Tym & Partners February 2005 T34E Slapton Coastal Zone Management Main Study Volume 3: Annex A - Consultation Addendum Prepared by Scott Wilson for Slapton Line Partnership August 2006Strategic Growth Areas
SGA1 | Derriford Development Framework Evidence Report | LDA Design | February 2009 |
SGA2 | Derriford and Seaton Area Action Plan Report on Proposed New District Shopping Centre | Cushman & Wakefield LLP | January 2011 |
SGA3 | Plymouth City Centre Development Study: Executive Summary | GVA | September 2014 |
SGA3A | Plymouth City Centre Development Study: Main Report | GVA | September 2014 |
SGA3B | Plymouth City Centre Development Study Appendix A (Heritage Audit and Statement of Significance) | Asset Heritage Consulting on behalf of GVA and Plymouth City Council | May 2014 |
SGA3C | Plymouth City Centre Development Study Appendix B (Plymouth Precinct Retail Study Design Appraisal) | NEW masterplanning on behalf of GVA and Plymouth City Council | September 2014 |
SGA4 | Plymouth City Centre Strategic Masterplan | LDA | February 2017 | LDA | February 2017 |
Other (includes infrastructure)
O1 | A Vision for Plymouth | MBM Arquitectes with AZ Urban Studio | October 2003 |
O2 | South Hams Local Development Framework Strategic Infrastructure Delivery Plan | South Hams District Council | 2010 |
O3 | West Devon Infrastructure Delivery Plan | West Devon Borough Council | February 2015 |
O4 | Education Infrastructure Plan (revised) 2016 to 2033 | Devon County Council | 2016 |
O5 | Plymouth and South West Devon Joint Local Plan Viability Study | PBA | February 2017 |
O6 | South Hams and West Devon Village Sustainability Assessment Framework | Plymouth City Council, South Hams District Council and West Devon Borough Council | February 2017 |
O7 | Plymouth Plan Part One Refresh | Plymouth City Council | March 2017 |
O8 | South West Devon Infrastructure Planning Evidence Base Report | Devon County Council | June 2017 |
O9 | Plymouth and South West Devon Infrastructure Needs Assessment: Main Report | Plymouth City Council, South Hams District Council, West Devon Borough Council and Devon County Council | July 2017 |
O9A | Plymouth and South West Devon Infrastructure Needs Assessment: Appendix 3 | Plymouth City Council, South Hams District Council, West Devon Borough Council and Devon County Council | July 2017 |
O9B | Plymouth and South West Devon Infrastructure Needs Assessment: Appendix 4 | Plymouth City Council, South Hams District Council, West Devon Borough Council and Devon County Council | July 2017 |
O10 | Plymouth and South West Devon Plan for Infrastructure and Investment | Plymouth City Council, South Hams District Council, West Devon Borough Council and Devon County Council | July 2017 |
O11 | Plymouth Policy Area Education Infrastructure Planning Evidence Base Report | Plymouth City Council | July 2017 |
O12 | Minerals Topic Paper 1 Spatial Strategy Version 2 | Dartmoor National Park, Devon County Council, Plymouth City Council and Torbay Council | January 2016 |
O13 | Minerals Topic Paper 2 Safeguarding Mineral Resources & Infrastructure Version 2 | Dartmoor National Park, Devon County Council, Plymouth City Council and Torbay Council | January 2016 |
O14 | 5th Devon Local Aggregate Assessment 2006-2015 Version 2 | Devon County Council | August 2016 |
O15 | 6th Devon Local Aggregate Assessment 2007-2016 | Devon County Council | July 2017 |
O16 | Plymouth Report | PCC | October 2017 |
The past consultation documents used in the preparation of the Plymouth and South West Devon Joint Local Plan are available to view on the Plymouth and South West Devon Joint Local Plan: Past consultation (Regulation 18 and 19) page.